October 15, 2026
In 2026, Juban Road has been given three different finish dates, and none of them has come with a ribbon cutting. In March, the Louisiana Department of Transportation and Development said the widening between I-12 and US 190 would be done by the end of May. In late May, the target moved to September. As of this week, DOTD's own construction roster still lists the project as under construction, with an estimated completion of "Fall of 2026."
The bigger change is where the orange barrels go next. One lane-closure project already started south of I-12 in August. Others are scheduled on I-12 itself, on dates that reach into 2029. Meanwhile, Juban Crossing's most talked-about arrival, a Target store, is on the company's list of upcoming stores without an opening date. For anyone who drives this corridor every week, the useful question is which piece of construction comes next, and when.
The widening has a long history. WBRZ reported in March 2026 that the project went to bid in 2018 and broke ground years later. In the same story, DOTD's Rodney Mallett said the roundabout had recently opened "in its correct and final configuration," and that "we have seen the traffic improve greatly in this area." Crews were finishing drainage work before they could open the remaining lanes, and DOTD expected the job to wrap up by the end of May.
By May 29, the remaining work was permanent striping, sidewalks and landscaping. WBRZ's follow-up put completion in September 2026. We have not found a September or October report confirming that the project is finished.
DOTD's District 62 construction page, updated October 7, 2026, still lists two Juban Road widening contracts for the I-12 to US 190 stretch. One is a $20.9 million asphalt widening by Kort's Construction Services, with a work order dated February 2024 and an estimated completion of "Fall of 2026." The other is a $15.3 million concrete pavement contract by KCR Contractors, with a 2019 work order and an estimate of "Fall of 2025." The same page still lists a 2018 roundabout contract at US 190 and LA 1026 with an estimated completion of "End of 2019." So the roster shows what the state has under contract. It is not a daily report on which lanes are open. Even so, it is the most recent official status available, and it does not yet show the widening as complete.
While the north side of the interchange heads toward its last punch list, a separate DOTD project began on the south side. According to Livingston Parish News, a $1.7 million pavement and drainage job covers 2.65 miles of LA 1026 from LA 16 to Forrest Delatte Road. Work started August 24, with nighttime alternating lane closures that keep at least one lane open, and completion is targeted for the fourth quarter of 2026.
So the stretch of Juban Road that most drivers used to get around the northern construction now has its own work zone, at least after dark. Both projects are set to end around the same time this fall, if their schedules hold.
A few miles away, DOTD began a $1.6 million realignment of about a third of a mile of LA 16 at Gourdon Lane on Monday, October 5. The department expects it to be finished by the end of November and puts traffic on that segment at about 6,000 vehicles per day.
Many people in Denham Springs and Walker reach Juban Road by way of I-12, and the interstate has its own schedule. This is how DOTD and local reporting lay it out as of early October 2026:
| Project | Where | What it is | Reported timing |
|---|---|---|---|
| Median barrier retrofit | I-12 between O'Neal Lane and Range Avenue | Alternating overnight lane closures, at least one lane open each way | October 5 to 10, 2026 |
| LA 16 realignment | LA 16 at Gourdon Lane | About one-third mile realigned, $1.6 million | October 5 to end of November 2026 |
| LA 1026 overlay and drainage | LA 16 to Forrest Delatte Road | 2.65 miles, nighttime closures | Started August 24; target Q4 2026 |
| I-12 asphalt overlay | Livingston Parish line to Satsuma Road | Preservation overlay, about $15 million estimated | Q1 2027 to mid-2028 |
| Hog Branch bridge replacement | I-12 | $31.2 million contract, JB James Construction | Work order July 1, 2026; est. Fall 2029 |
| LA 447 widening | I-12 to Buddy Ellis | Widening, access management, roundabouts | Still in design |
The I-12 overlay is resurfacing to extend the life of the existing road and improve the ride. It is not another widening. In July, Livingston Parish News reported that DOTD expects it to start in the first quarter of 2027 and finish in mid-2028. The LA 447 widening toward Buddy Ellis is listed in DOTD's FY 2026–27 highway program at the design and development stage, with a note that it needs Division of Administration approval before it can be bid. The program also warns that projects still in development may change before they are approved for construction.
Put the dates side by side and the pattern is clear. Construction around Juban moves from one road to the next. The surface street wraps up this fall, the interstate overlay follows in early 2027, and the Hog Branch bridge estimate runs to fall 2029.
The shopping side of the corridor follows a similar pattern. The arrivals you can visit today are smaller than the ones people are waiting for.
Dave's Hot Chicken opened in March 2026 at 27306 Crossing Circle, in the former Moe's Southwest Grill space at Juban Crossing, next to Marble Slab Creamery and Mattress Firm. WAFB reported a company spokesperson confirming an opening day of Friday, March 20. The restaurant's location page now lists its hours and online ordering.
Empire Wingz opened its ninth location on Saturday, August 29, 2026, on Bass Pro Boulevard near Bass Pro Shops in Denham Springs, according to WBRZ. The Livingston Parish Chamber's grand-opening notice, posted September 1, lists the address as 120 Bass Pro Blvd., Suite E, and mentions menu items like Deucey Juice and VJ Fries.
Target is the one people ask about. The retailer confirmed to The Advocate that it plans a store of about 148,000 square feet at the northwest corner of Juban Road and Juban Crossing Boulevard. That is a little smaller than the two Baton Rouge Targets, both of which opened more than 20 years ago. Target bought the land for $6.2 million, and the Livingston Parish Planning Commission had already unanimously approved a final site plan for "Juban Crossing Phase 3" in December. It would be the parish's first Target. Today, the closest one is on Millerville Road in Baton Rouge, which The Advocate put at about 15 minutes from Juban Crossing.
Denham Springs now appears on Target's upcoming-stores page at that same corner, with no opening date. The company told The Advocate it would share the grand-opening date as the opening gets closer. We have not found any public report of a construction start or hiring.
Dutch Bros Coffee proposed a 986-square-foot drive-through between the McDonald's and the RaceTrac at Juban Crossing. WBRZ reported on March 30, 2026 that the site plan would go before the Livingston Parish Planning Commission on April 7. At that point, The Advocate noted, construction had not officially begun. We have found no later report that the store has opened.
A Target site plan, a coffee drive-through still at the hearing stage, and a road project on its third finish date all have one thing in common: none has a confirmed date to put on a calendar yet. What you can count on today is two new places to eat, an overnight lane closure on LA 1026 through the fourth quarter, and an I-12 overlay scheduled to start in the first quarter of 2027.
At Debra Sullivan, we keep an eye on these Juban corridor dates because they shape everyday drives and errands for the Livingston Parish families we work with. If you'd like to talk through how the road schedule or a future Target fits with plans for your own home near Juban Road, we're happy to help. Contact Us.